Rehabilitation And Upgradation

Package -A
Package-A envisages rehabilitation of the State Highway and Major District Roads in Kasargod District for a length of 25 Km DBFOMT (Design, Build, Finance, Operate, Maintain and Transfer) on Annuity basis. The project roads are listed below :-
  • Vidyanagar-Seethangoli Road – 9.40 Km
  • Uppala-Kaniyana Road – 15.60 Km
The construction of the above project roads has been completed and I naugural ceremony held on 24.11.2017 at Uppala, Kasargode by the Hon’ble Minister for Works and Registration. The construction period was one year and Project Cost is Rs.81 Crores. Operation & Maintenance Period is ongoing
Package -B
Package-B envisages rehabilitation of the State Highway and Major District Roads in Kottayam and Thiruvananthapuram Districts for a length of 58 Km DBFOMT (Design, Build, Finance, Operate, Maintain and Transfer) on Annuity basis. The project roads are listed below:-
  • Vellanad-Chettachal Road – 21.90 Km
  • Kanjirappally-Kanjiramkavala Road – 36.10 Km
The Operation & Maintenance period of 13 years is started 27.10.2018 onwards.

Ongoing Projects

Karamana -Vellarada Road :-
As per GO (Rt) No.355/2016/PWD Dated:15.02.2016 Government accorded Administrative Sanction for Land Acquisition for Rs.21.74 Cr. 6(1) Notification was published as per Notification No.LA2.545/2016 dated: 16.03.2017. Boundary stones have been laid for the entire stretch from Km 0 to 35.50 Km for acquiring the land. Contingency charges remitted to Special Tahasildar LA, PMG Thiruvananthapuram of Rs.1.07 Cr. on 30.01.2019. Joint inspection with Revenue officials for the entire 35.5 Kms is completed. Revised DPR after avoiding insignificant bus bays is submitted to the Principal Secretary, Public Works Department for Administrative Sanction on 04.12.2019. The Expert Committee report for the first 5.5 km from Karamana to Kundamankadavu recommending to take up 1.1356 Hectare land for road widening is published. From 5.5 Km to 20 Km, Social Impact Assessement Study is in progress, after publication of 4(1) notification.
KIIFB PROJECTS
Land Acquisition in Progress
Improvements to Kozhikkode-Balussery Road (20.32 Km) :-
Funding and Sanction Order was received from KIIFB vide Proceedings of the Chief Executive Officer No.APR-2/330/2017/KIIFB dated.21/12/2017 for an amount of Rs.88.92 Cr. Government issued Administrative Sanction vide GO (Rt) No.803/2018/PWD dated:06/05/2018 for an amount of Rs.3.26 Cr for Land Acquisition. The 6(1) notification was published on 16.07.2019. As per direction of KIIFB first 4 Km Karaparambu to Kakkodi bridge followed by Urban Master Plan for a width of 18m. The boundary stone laying of initial 4 km done by following City Master Plan of Kozhikode District. 4(1) Notification published. Boundary stone relaying completed and inspection of revenue completed. Addressed all utility providers for estimate submission. Joint Inspection with KSEB, KWA and BSNL has completed. Contingency charge of Rs.50 Lakh was remitted to the Special Tahsildar LA (KCRIP),Kozhikode on 11.02.2020. SIA public hearing conducted. SIA final report from Centre for Management Development received. Expert Committee was formed for reviewing SIA report by agency. Report from the Expert Committee is awaited.
Improvements to Erattupetta-Peerumedu-Wagamon Road (23.80) Km :-

Funding and sanction order received from KIIFB vide Proceedings of the Chief Executive Officer No.APR-2/330/2017/KIIFB dated: 21.12.2017 for an amount of Rs.63.99 Crores. Government issued an Order (GO(Rt) No.801/2018/PWD dated:06.05.2018) for an amount of Rs.4.458 Cr. for Land Acquisition. 6(1) notification published.

The boundary stone laying work was completed up to 17 Kms and now as per the direction from KIIFB based on the revised guidelines dated 20th November 2018 these stones are relaying to a RoW of 12 metre.

Improvements to Thiruvalla-Mallappally-Chelakombu Road (20.4 Km) :-

Funding and Sanction Order received from KIIFB vide Proceedings of the Chief Executive officer No.APR-2/330/2017/KIIFB dated.21/12/2017 for an amount of Rs.81.57Cr. As per G.O.(Rt)No.892/2018/PWD  dated:24/05/2018 Government accorded Administrative Sanction for Land Acquisition for Rs.10.70 Cr. 6(1) notification is published on 13.08.2018 No.2155.

As per the direction of KIIFB, RoW of the sretch of road from Mallappally to Chelakombu changed to 10 metre and relaying of boundary stones are completed. Also the boundary stones at bell mouths and the areas where buildings affected are rearranged.

The survey work of the road from Chelakombu to Nedumkunnam Church junction in Changanassery-Manimala road was completed

The boundary stone laying work was completed. The alignment sketch along with Form No.2 submitted to Revenue Department for further Land Acquisition procedures.

KIIFB PROPOSAL-2017-2018
  • Muhamma-Thaneermukkam-Kayaloram Road
  • Vaikkom-Toll-Chemmanakari Road
In the meeting of the Board of Directors the Hon’ble Chairman has instructed to drop the above works. Government have appointed RICK Ltd as the SPV for the above works as per GO (Rt) 1167/2017/PWD dated 5.8.2017. Hence, necessary proposals to cancel the appointment of RICK Ltd as SPV to the above projects shall be furnished to Government.